# Inside the 350 MW Grid Connection Powering Britain's Biggest Battery Factory

[![David Coleman](/uploads_resolved/images/261/320.webp) Author profile for David Coleman](/authors/david-coleman/ "Author profile for David Coleman")[LinkedIn profile for David Coleman](https://www.linkedin.com/in/david-martyn-coleman/ "LinkedIn profile for David Coleman")[David Coleman](/authors/david-coleman/ "Author profile for David Coleman")

Founder & Renewable Energy Author, kilowatts.uk

Article

# Inside the 350 MW Grid Connection Powering Britain's Biggest Battery Factory

Published 2026-11-19 20:03:14 Updated 2026-11-19 12:03:55

Main works are underway on the 400 kV grid connection for Agratas’s Somerset battery gigafactory. See how it will meet 350 MW of campus demand.

![Create a wide, photorealistic editorial illustration of a high-voltage substation under construction in the Somerset Levels near Woolavington. Show flat pasture, hedgerows, an…](/uploads_resolved/images/1229/320.webp)

 [   Preferred on Google  ](https://www.google.com/preferences/source)

![Create a wide, photorealistic editorial illustration of a high-voltage substation under construction in the Somerset Levels near Woolavington. Show flat pasture, hedgerows, an…](/uploads_resolved/images/1228/320.webp)

## Inside the 350 MW Grid Connection Powering Britain's Biggest Battery Factory

How agratas battery factory grid connection work, typical output, costs and limits, and whether they have a future for UK homes, balconies and businesses.

## The 350 MW grid connection planned for Agratas’s Somerset battery factory

National Grid Electricity Transmission is building a 400/132 kV substation near Woolavington, Somerset, to connect the Gravity Smart Campus to Britain’s transmission network. The permanent connection is designed to meet around 350 MW of demand across the campus, including the Agratas electric vehicle battery factory. National Grid confirmed on 18 November 2026 that main construction was underway. Two interim 33 kV connections are supplying the Agratas site during construction. [National Grid construction announcement](https://www.nationalgrid.com/national-grid-starts-construction-somerset-substation-supporting-over-4500-new-jobs "Nationalgrid – National Grid construction announcement") · [National Grid connection case study](https://www.nationalgrid.com/electricity-transmission/connections/recent-projects/woolavington "Nationalgrid – National Grid connection case study")

Agratas plans to manufacture around 40 GWh of battery cells a year once all phases are complete. The Competition and Markets Authority’s Subsidy Advice Unit says this would make Agratas the UK’s largest battery manufacturer by planned capacity. [CMA Subsidy Advice Unit report on Agratas](https://assets.publishing.service.gov.uk/media/696f5e2c011505255b2d4201/Subsidy_Advice_Unit_Report_on_the_proposed_subsidy_to_Agratas_Limited.pdf "GOV.UK – CMA Subsidy Advice Unit report on Agratas")

## How the 400 kV connection will supply the campus

Existing substations in the area lacked the capacity to serve the development. National Grid chose a site beneath an existing 400 kV overhead line so it could connect the new substation without adding pylons or overhead wires. Supergrid transformers at Woolavington will step the voltage down from 400 kV on the transmission side to 132 kV for the onward connection. [Woolavington substation project page](https://www.nationalgrid.com/electricity-transmission/network-and-infrastructure/infrastructure-projects/woolavington-substation "Nationalgrid – Woolavington substation project page") · [National Grid connection case study](https://www.nationalgrid.com/electricity-transmission/connections/recent-projects/woolavington "Nationalgrid – National Grid connection case study")

National Grid Electricity Distribution installed the two interim 33 kV connections so Agratas could start building the factory while National Grid developed the permanent connection for the campus’s longer-term demand. [National Grid connection case study](https://www.nationalgrid.com/electricity-transmission/connections/recent-projects/woolavington "Nationalgrid – National Grid connection case study")

## What 400 kV, 350 MW and 40 GWh per year measure

The incoming transmission line operates at 400 kV. The permanent connection is designed to accommodate around 350 MW of electrical demand across the campus. Electricity consumption over a given period depends on how much power the campus draws and for how long. [National Grid connection case study](https://www.nationalgrid.com/electricity-transmission/connections/recent-projects/woolavington "Nationalgrid – National Grid connection case study") · [Woolavington substation project page](https://www.nationalgrid.com/electricity-transmission/network-and-infrastructure/infrastructure-projects/woolavington-substation "Nationalgrid – Woolavington substation project page") The Environment Agency gives the factory’s planned manufacturing capacity as around 40 GWh per year. That figure adds up the energy storage capacity of the cells the factory is designed to make in a year. The CMA report ties that capacity to completion of all project phases. [Environment Agency project overview](https://engageenvironmentagency.uk.engagementhq.com/wessex-regulated-industry-sites/widgets/123562/faqs "Engagementhq – Environment Agency project overview") · [CMA Subsidy Advice Unit report on Agratas](https://assets.publishing.service.gov.uk/media/696f5e2c011505255b2d4201/Subsidy_Advice_Unit_Report_on_the_proposed_subsidy_to_Agratas_Limited.pdf "GOV.UK – CMA Subsidy Advice Unit report on Agratas")

## Overview

The distinction between power and stored energy also matters when sizing [batteries for business premises](https://kilowatts.uk/resources/commercial-battery-storage-for-uk-businesses/ "commercial battery storage for uk businesses").

## When will Woolavington substation be ready?

National Grid is aiming to finish construction in summer 2029. Early work included laying foundations and preparing the existing overhead line for the connection. The main build includes above-ground steelwork and major electrical equipment. Three supergrid transformers are expected to arrive in early 2027. [Woolavington substation project timetable](https://www.nationalgrid.com/electricity-transmission/network-and-infrastructure/infrastructure-projects/woolavington-substation "Nationalgrid – Woolavington substation project timetable") · [National Grid construction announcement](https://www.nationalgrid.com/national-grid-starts-construction-somerset-substation-supporting-over-4500-new-jobs "Nationalgrid – National Grid construction announcement")

Woolavington Parish Council reported on 13 October 2026 that main works were underway. The summer 2029 construction target may change. The permanent connection’s first energisation and the factory reaching full production each have their own timetable. [Woolavington Parish Council’s October 2026 update](https://woolavington-pc.gov.uk/news/national-grid-update-october-2026/ "Woolavington Parish Council – National Grid update for October 2026") · [Woolavington substation project timetable](https://www.nationalgrid.com/electricity-transmission/network-and-infrastructure/infrastructure-projects/woolavington-substation "Nationalgrid – Woolavington substation project timetable")

## What residents and businesses near Woolavington can expect

National Grid’s normal working hours are 8 am to 6 pm on weekdays and 8 am to 1 pm on Saturdays. Some deliveries or construction work may take place outside those hours. National Grid says it will give advance notice of work that could affect residents, businesses or local roads. Check the project updates when planning deliveries or journeys around the site. [National Grid construction announcement](https://www.nationalgrid.com/national-grid-starts-construction-somerset-substation-supporting-over-4500-new-jobs "Nationalgrid – National Grid construction announcement") · [Woolavington substation project updates](https://www.nationalgrid.com/electricity-transmission/network-and-infrastructure/infrastructure-projects/woolavington-substation "Nationalgrid – Woolavington substation project updates")

National Grid’s November announcement estimates that the factory will support around 4,600 direct jobs once fully operational. National Grid also announced a £530,000 fund for projects that benefit communities near the substation. It expects applications to open in 2027. [National Grid construction announcement](https://www.nationalgrid.com/national-grid-starts-construction-somerset-substation-supporting-over-4500-new-jobs "Nationalgrid – National Grid construction announcement")

## What the project shows about planning a new electricity supply

If you’re expanding a business site, estimate how much power each phase will need and when. Half-hourly electricity data can show when demand is highest. If your readings are in kWh per half hour, double each reading to get the average power in kW for that interval. Allow separately for brief peaks, such as motors starting, that a half-hour average can hide. That demand profile can also help you [compare solar for factories](https://kilowatts.uk/services/industrial/renewable-energy/industrial-solar-panel-installation/compare/ "Compare industrial solar options") against the hours when your site uses the most electricity.

Estimate the extra demand from new machinery, heat pumps or [EV charging points](https://kilowatts.uk/resources/ev-charging-station-installation-introduction/ "ev charging station installation introduction"), taking into account which could run at the same time. Give your distribution network operator the breakdown and proposed installation dates. It can assess whether your existing supply can handle the extra demand and whether an upgrade could affect your opening date.

If you’re considering solar and battery storage for a home or small business, use your smart-meter data to see when you use electricity and compare that with when you expect surplus solar generation. When [sizing a home battery](https://kilowatts.uk/resources/what-size-battery-do-i-need-for-my-home-in-the-uk/ "what size battery do i need for my home in the uk") or specifying storage for a business, ask installers to show the battery’s usable capacity in kWh and its continuous discharge power in kW. Usable capacity tells you how much energy the battery can deliver. Continuous discharge power tells you how much of your demand it can meet at any one time.

Tags: [Agratas somerset battery factory](/tags/agratas-somerset-battery-factory/ "Agratas somerset battery factory")[Mw grid connection](/tags/mw-grid-connection/ "Mw grid connection")[Gravity smart campus](/tags/gravity-smart-campus/ "Gravity smart campus")[Woolavington substation](/tags/woolavington-substation/ "Woolavington substation")[National grid somerset substation](/tags/national-grid-somerset-substation/ "National grid somerset substation")[132 kv somerset substation](/tags/132-kv-somerset-substation/ "132 kv somerset substation")[Agratas interim 33 kv connections](/tags/agratas-interim-33-kv-connections/ "Agratas interim 33 kv connections")[Somerset ev battery gigafactory](/tags/somerset-ev-battery-gigafactory/ "Somerset ev battery gigafactory")[Britain s biggest battery factory](/tags/britain-s-biggest-battery-factory/ "Britain s biggest battery factory")[Gravity smart campus transmission connection](/tags/gravity-smart-campus-transmission-connection/ "Gravity smart campus transmission connection")

 [   Preferred on Google  ](https://www.google.com/preferences/source)

Solar comparison

## Compare solar for your property

Enter your postcode to assess your roof, compare solar options and get quotes from UK installers.

- Free postcode start
- Home, business and industrial
- RoboMo™ maps your roof

## See which panels fit your roof

Choose home, business or industrial, then enter your postcode. RoboMo maps the roof and ranks panel brands by fit.

- Home
- Business
- Industrial

UK postcode

Fast, free and no obligation to proceed.

**1. Postcode** Start the assessment for your property.

**2. Pin the roof** Mark the array on the map.

**3. Compare** RoboMo™ builds your options.

![Battery storage ROI calculator](/uploads_resolved/images/1012/320.webp)

Battery ROI tool

## See what a battery saves on your bill

Enter the day rate, off-peak rate and export rate. The calculator ranks batteries in the Kilowatts shop over 10 years. Home batteries also suit offices and small commercial sites.

[ **Home** Houses and flats ](/services/residential/renewable-energy/residential-solar-panel-installation/batteries/)[ **Business** Offices and small sites ](/services/commercial/renewable-energy/commercial-solar-panel-installation/batteries/)[ **Industrial** Factories and warehouses](/services/industrial/renewable-energy/industrial-solar-battery-storage/#get-quote-now)

[Shop batteries](/shop/kilowatts-uk/range/solar-batteries/)

 ## Related services

- [keeping critical industrial circuits running](/services/industrial/backup-systems/industrial-critical-circuit-backup/)
- [keeping workplace chargers running in a power cut](/services/commercial/backup-systems/commercial-ev-charger-backup/)
- [commercial underfloor heating](/services/commercial/heating-cooling-ventilation/commercial-underfloor-heating/)
- [air source heat pumps for industrial buildings](/services/industrial/heating-cooling-ventilation/industrial-air-source-heat-pump/)
- [solar panels for factories and warehouses](/services/industrial/renewable-energy/industrial-solar-panel-installation/)

 Reading

## Sources and further reading

[![Commercial solar plus battery for UK factories: UK business](/uploads_resolved/images/815/320.webp)Commercial solar plus battery for UK factories: UK business

See when commercial solar plus a battery fits a UK factory: shift timing, export caps and connection headroom. A standard battery is not backup power.

Read article](/resources/commercial-solar-plus-battery-for-uk-factories/ "Commercial solar plus battery for UK factories: UK business")[![What size home battery do you need in the UK?](/uploads_resolved/images/995/320.webp)What size home battery do you need in the UK?

What battery do I need depends on usable kilowatt-hours you can shift, inverter power, and whether the charge window and connection can fill it.

Read article](/resources/what-battery-do-i-need/ "What size home battery do you need in the UK?")[![Flower Turbines UKPN approval: what does it mean?](/uploads_resolved/images/425/320.webp)Flower Turbines UKPN approval: what does it mean?

Discover what Flower Turbines' UK Power Networks approval means for small wind buyers in the UK, and how it affects their projects.

Read article](/resources/flower-turbines-ukpn-approval-what-it-means-for-uk-grid-connection/ "Flower Turbines UKPN approval: what does it mean?")[![Can A Home Battery Charge From The Grid? UK Guide](/uploads_resolved/images/658/320.webp)Can A Home Battery Charge From The Grid? UK Guide

Yes - a home battery can fill from cheap off-peak grid electricity, then run your house through the expensive peak. Here's how it works in UK homes.

Read article](/blog/home-battery-charge-from-grid-off-peak/ "Can A Home Battery Charge From The Grid? UK Guide")

 Solar panels

## Solar panels

[![DAS-DH108NE 530W](/images/panels/das-solar-das-dh108ne-500.jpg)

530WDAS-DH108NE 530W

DAS Solar

DAS Solar · 530W

View details](/services/residential/renewable-energy/residential-solar-panel-installation/solar-panels/das-solar-das-dh108ne-530/)[![LONGi Hi-MO 6 Explorer 585W](/images/panels_resolved/longi-himo-6-explorer-585w/320.webp)

585WLONGi Hi-MO 6 Explorer 585W

LONGi Solar

LONGi Solar · 585W

View details](/services/residential/renewable-energy/residential-solar-panel-installation/solar-panels/longi-himo-6-explorer-585w/)[![AIKO Neostar 3S54 A495-MCE54Mb 495W](/images/panels/aiko-neostar-3s54-a495-mce54mb-495w.jpg)

495WAIKO Neostar 3S54 A495-MCE54Mb 495W

AIKO Solar

AIKO Solar · 495W

View details](/services/residential/renewable-energy/residential-solar-panel-installation/solar-panels/aiko-neostar-3s54-a495-mce54mb-495w/)

 Shop

## Shop

[![Growatt MIN 10000 TL-X2](/images/shop/inverter-growatt-min-10000-tl-x2-13.jpg)

£870.00Growatt MIN 10000 TL-X2

View product](/shop/kilowatts-uk/inverter-growatt-min-10000-tl-x2-13/)[![LuxpowerTek SNA 6K Off-Grid](/uploads_resolved/images/1230/320.webp)

£708.00LuxpowerTek SNA 6K Off-Grid

View product](/shop/kilowatts-uk/luxpowertek-sna-6k-off-grid/)[![LuxpowerTek SNA 14K Off-Grid](/uploads_resolved/images/1091/320.webp)

£1,474.00LuxpowerTek SNA 14K Off-Grid

View product](/shop/kilowatts-uk/luxpowertek-sna-14k-off-grid/)

 ## Mo's Mission Nominations

[Garlinge Primary School and Nursery is a foundation primary school on Westfield Road in Margate, Kent, for children aged 3 to 11. It is m...](/solar-mission/garlinge-primary-school-nursery/)

[St Luke's Church of England Primary School is a voluntary controlled Church of England primary school on Jubilee Road in Formby, Merseysi...](/solar-mission/st-luke-s-church-of-england-primary-school/)

[Comberbach Nursery and Primary School is a primary academy on Mather Drive in the village of Comberbach, near Northwich in Cheshire, for...](/solar-mission/comberbach-primary-school/)

 ## Solar installation near you

Write for Kilowatts.uk

## Got a trade and something worth saying?

Write it here under your own name. Sign in, put a profile up, and start a guide. Pay only if you want more links from your articles out to your own site.

### Register

Create a Kilowatts.uk account, or sign in if you already have one.

### Author profile

Put your name, photo and experience on a public author page.

### Start creating

Write a guide or a blog. Free authors can put one followed link to their own site in articles each month.

[Write for us](/write-for-us/) [Register or sign in](/login/)

## Frequently Asked Questions

### What does the 350 MW grid connection supply?

The permanent connection is designed to meet around 350 MW of electrical demand across the Gravity Smart Campus in Somerset, including the Agratas battery factory. The campus’s actual electricity consumption will depend on how much power it draws and for how long.

### Why does the battery factory need a new substation?

Existing substations in the area lacked the capacity to serve the development. The new Woolavington substation will connect to an existing 400 kV overhead line and step the voltage down to 132 kV for the campus.

### When will Woolavington substation be ready, and how is the factory site powered in the meantime?

National Grid is aiming to finish construction in summer 2029. The permanent connection’s first energisation and the factory reaching full production each have their own timetable. Two interim 33 kV connections supply the Agratas site during construction.

### What does 40 GWh of battery production per year mean?

It is the combined energy storage capacity of the battery cells Agratas plans to manufacture in a year once all phases are complete. A gigawatt-hour measures energy, while the grid connection’s 350 MW rating measures power.

### What can residents expect during the Woolavington substation works?

National Grid lists normal working hours as 8 am to 6 pm on weekdays and 8 am to 1 pm on Saturdays. Some work or deliveries may take place outside those hours. National Grid says it will give advance notice of work that could affect residents, businesses or local roads.

### Will I need a bigger electricity supply for a heat pump or EV charger?

It depends on your existing supply and what else may be running at the same time. Ask your installer to assess the combined demand from the new equipment and your existing appliances. Your local distribution network operator can confirm whether the supply can handle the extra demand or needs an upgrade.

### What should I compare when buying a home battery?

Compare usable capacity in kWh and continuous discharge power in kW. Usable capacity tells you how much energy you can draw from the battery, while discharge power tells you how much demand it can meet at once. If you have solar panels, use your smart-meter data to see when you import electricity and compare that with when you expect surplus solar generation.